TMG7800 Controller Replacement
William Wong (Talk | contribs) (→Removing the Defective Unit) |
William Wong (Talk | contribs) (→Installing the Replacement Unit) |
||
Line 22: | Line 22: | ||
*Remove the faulty/TMG7800 from the equipment rack | *Remove the faulty/TMG7800 from the equipment rack | ||
− | == Installing the Replacement | + | == Installing the Replacement/Additional Controller == |
'''Refer to [[Gateway_Installation#TMG7800|TMG7800 Installation guide]]''' | '''Refer to [[Gateway_Installation#TMG7800|TMG7800 Installation guide]]''' | ||
− | *Rack-mount the Replacement | + | *Rack-mount the Replacement/Additional Controller |
− | *Connect to the Management | + | *Connect to the Management network |
− | *Connect to the | + | *Connect to the Control network |
− | + | ||
== Starting Up the TMG7800 == | == Starting Up the TMG7800 == |
Revision as of 02:33, 29 November 2018
This procedure is used to replace a faulty controller with a new controller or add a new controller to existing single controller system.
Contents |
Prerequisite
Prior to replacing faulty controller or add new controller to the system, you must have the following:
- You must have ordered and obtained new TMG7800 server controller from Telcobridges
- In case of 3.0 system, you must have already a 3.0 TMG7800 Controller whether completing TMG7800 Baremetal Installation
Backup your system configuration
Before Proceeding with the procedure, it is a must to backup your configuration from other controller which is running normally. Please follow this link: Backup procedure
Note: The database backup should be done and stored at a safe place regularly
Upload your backup system configuration
After backup the configuration from other controller, upload the configuration to the new controller by following this link: Upload Configuration
TMG7800 Controller Replacement/Addition Procedure
Removing the Defective Unit
This procedure is required for replacing existing controller
- Shutdown the faulty/TMG7800 controller
- Disconnect the faulty/TMG7800 controller from existing network where the other controller is residing
- Remove the faulty/TMG7800 from the equipment rack
Installing the Replacement/Additional Controller
Refer to TMG7800 Installation guide
- Rack-mount the Replacement/Additional Controller
- Connect to the Management network
- Connect to the Control network
Starting Up the TMG7800
- Power up the TMG7800
Pushing the configuration to the replacement unit
1- Upload the license of the new unit in the system. See Uploading a license.
2- Connect to web portal and access the Hardware Units page:
Hardware Units
3- Identify the unit to replace and select it.
4- Replace the Serial Number of the unit and Save. If the Name is the same as the Serial Number, we suggest to change this as well.
5- Activate the configuration.